                              (EuroCities, 2013a). Budget: 79,649,455 PLN (Polish złotych) (CA. 21 million EUR). The distribution of
                              the budget for the four phases of the project is shown in figure 5.


                   PROCEEDINGS OF THE 11 TH  ADMINISTRATION AND PUBLIC MANAGEMENT INTERNATIONAL CONFERENCE
                                                      Total amount   Co-financing European funds
                                                                              27007

                                                              21192                          19343
                                                                                  16046
                                              12107               11395


                                                                                                 5686
                                                  2768



                                           2006 - 2007     2007 - 2009     2008 - 2011    2011 - 2012

                                             FIGURE 5. BUDGET DISTRIBUTION FOR THE 4 PHASES OF THE PROJECT (PLN)
                                     Source: Bydgoszcz City Hall, 2011; Loose, 2011, p. 67; Szczesik-Zobek and Loose, 2011, p. 32
                        30 th  – 31 st  October 2015  ”Strategic Management for Local Communities”   Bucharest   persons in the area who are experiencing problems related to work, or have difficulties in finding a job,
                              The project’s beneficiaries: the residents in the Polish city Bydgoszcz, employees and unemployed


                              SMEs that operate in the area, entrepreneurs who want to open up a new business on Mille Island or
                              nearby.

                              The regeneration process was divided into four major phases that have considered (Bydgoszcz City

                              Hall, 2011; Loose, 2011; Szczesik-Zobek and Loose, 2011; EuroCities, 2013b):

                                 1.  Revitalizing Mill Island for business development (existing or new) (2006-2007) (figure 6) took
                                     into consideration: building three bridges that have linked the island with the rest of the city; the

                                     reconstruction of the  Miedzywodzie channel; restoration of a historic building and turning it into
                                     a center for employment and business support.




















                                                FIGURE 6. REVITALIZING MILL ISLAND FOR BUSINESS DEVELOPMENT
                                                             Source: Loose, 2011, p. 18